Pre-Completion
Testing... SOUND

In July 2003 the new Approved Document
E of the Building Regulations came into force. This
requires that at least 10% of all new residential properties
are tested to demonstrate that the levels of sound insulation
provided between adjacent dwellings are in compliance
with Building Regulations. Companies who carry out the
testing should be either UKAS Accredited or ANC Registered.
The regulations were revised in 2004 to clarify the
2003 document and correct errors. To download the full
documents click on the image to the right or visit
the Approved Documents page on the Planning Portal government
website.
Does
it apply to me?
Yes - if you have recently built or refurbished
any residential property that is directly linked to
another property (ie excluding detached dwellings).
I've never had to do pre-completion
testing before, why now?
Part E requirements were revised in 2003
to combat the increasing number of noise complaints
resulting from poor acoustic insulation between dwellings.
It is intended that reduced sound transmission between
dwellings will offer residents a better quality of life.
What types of tests need to be done?
There are two types of sound
test - airborne and impact. Airborne tests are carried
out on walls and floors separating dwellings, impact
tests are carried out on floors separating dwellings.
How many pre-completion tests do I
need to have?
For every 10 dwellings within a property
1 complete dwelling will need to be tested. The number
of tests within that dwelling will depend on the number
of walls or floors between adjoining dwellings. If multiple
wall or floor constructions are used - tests will need
to be carried out on each type of construction. A typical
flat in a large block will require 6 separate tests
- 2 impact tests (1 in the bedroom and 1 in the living
room), 2 vertical airborne tests across the separating
floor and 2 horizontal airborne tests across the separating
walls. A terraced house will only require 2 airborne
tests across the separating wall.
But what if I'm developing only two
attached dwellings?
The number of dwellings that require testing
is obtained by dividing the number of adjacent dwellings
by 10 then rounding up to the nearest 1, so for 2 dwellings
- 2/10 = 0.2 = 1. Therefore 1 dwelling would require
testing.
I've just refurbished an existing property
and developed it into flats. Do I require pre-completion
testing?
Yes - Any wall or floor separating adjacent
flats (see above) would need to be tested.
Which rooms within each dwelling will
be tested?
Pre-completion testing is conducted between
key living spaces where possible. Key living spaces
are bedrooms and living rooms. Testing is not carried
out between living spaces and corridors/stairwells.
Generally, the Building Control Officer will nominate
the partitions that he/she wants to be tested.
How are the pre-completion tests performed?
- Airborne tests are conducted
using loudspeakers and a sound level meter. The loudspeakers
are used to produce noise in one room (source) which
is then measured in the room on the other side of
any separating partition between dwellings (receiver).
Using additional acoustic measurements inside the
receiver room, the difference between the noise levels
in each room can then be calculated to give the sound
reduction of the separating partition.
- Impact tests are only performed
on floors between adjoining dwellings. The test is
performed using a standard "tapping" machine
and a sound level meter. The tapping machine is a
device that 'taps' on the floor emulating the sound
of people walking around or other objects 'impacting'
with the floor. The machine is turned on in the source
room and measurements are taken in the receiver room.
Using additional acoustic measurements inside the
receiver room, a value for the impact sound can then
be calculated.
What are the requirements of
Pre-completion testing?
Pre-completion testing requires
that walls and floors between new dwellings provide
at least 45 dB DnT,w+Ctr, and walls and floors between
refurbished dwellings provide at least 43 dB DnT,w+Ctr.
Floors between new dwellings must have a maximum of
62 LnT,w, and floors between refurbished dwellings must
have a maximum of 64 LnT,w.
What does DnT,w+Ctr mean?
DnT,w+Ctr is a expression of the
acoustic insulation of a partition. The higher the value,
the better the partition performs. The expression takes
into account background noise levels and reverberation
times in the receiver room and is the current standard
for measuring sound reduction between walls.
What does LnT,w mean?
LnT,w is the weighted standardised
impact sound pressure level and is used to express the
amount of noise present in the receiver room. A high
LnT,w value represents poor performance of the separating
partition. LnT,w incorporates receiver room acoustics
into its calculation and is the current standard measurement
for impact noise.
What happens if a partition within
my development does not meet the requirements?
In the event of a test not meeting
the requirements of Part E, the developer will be required
to perform remedial works to the relevant construction
and all similar constructions. Further pre-completion
testing of the treated constructions will then be required
to demonstrate that Part E requirements have ultimately
been met. Normally, Building Control will require an
increased percentage of dwellings to be tested following
a failed test.
I have used Robust details,
do I need pre-completion testing?
If you have registered the constructions
with Robust Details Ltd then pre-completion testing
is not required. If you have followed the robust detail
guidance but have not registered the constructions then
pre-completion testing will be required.
What are Robust Details?
Robust details are wall and floor
constructions that are expected to achieve part E requirements
and therefore do not require testing. As mentioned above
these need to be registered to avoid pre-completion
testing.
When should pre-completion testing
be carried out?
Pre-completion testing should be
carried out when the building is complete but not furnished.
All floors and walls should be finished and sealed but
second fixings are not essential. Carpets should not
be laid with the exception of those floors where the
carpet is an integral part of the floor (ie Floor type
1 in Approved Document E - "Concrete base with
ceiling and soft floor covering")
What conditions are needed on
site?
- Quiet conditions are preferred
so that tests can be carried out efficiently. However
with the appropriate testing equipment and procedures,
a degree of noise on site can be worked around, thus
minimising site downtime.
- A 240V supply should ideally
be available, either within the property or via an
extension. Otherwise a silenced generator is required
- Access to the rooms both side
of a partition is required.
How long does pre-completion
testing take?
Typically on-site testing of each
dwelling will take around an hour.
Who can carry out pre-completion testing?
Only
organisations accredited by the Association
of Noise Consultants
(ANC) or the United Kingdom Accreditation Service
(UKAS) can submit sound insulation test results to a
Building Control Body as proof of conformity to Part
E. Cass Allen Associates are an ANC-accredited organisation.
What happens after the tests
have been performed?
Data is analysed and the results
are uploaded to the Association of Noise Consultants
(ANC) for certification. Reports and certificates suitable
for submission to building control are then compiled
and issued.
I need pre-completion testing.
Contact
Cass Allen Associates on 0870 4427 456
|